Dredging for TT2

Attention, open in a new window. PDFPrintE-mail

Dredging for TT2 is progressing well, back inside the original window, with half of the anticipated volume of material being removed by 25th November.  The dredged material is being used to simultaneously in fill the Tyne Dock.  The continual monitoring provided by five water quality buoys has showed full compliance with the limits imposed by the Environment Agency.  The dredger is currently dredging the trench from mid river towards the North Bank, into Howden Basin. 